# Independent answer check

Build F2 with =DATE(B2,C2,D2): Tuesday Nov 24, 2026. Using the two fictional closure rows, enter =DATE(2026,11,26) in H2 and =DATE(2026,11,27) in H3. =WORKDAY(F2,E2) gives Monday Nov 30; =WORKDAY(F2,E2,H2:H3) gives Wednesday Dec 2. Counted days with closures: Nov 25 day 1, Nov 30 day 2, Dec 1 day 3, Dec 2 day 4.

Independent calendar count: Nov 24 is Tuesday. Skip Nov 26–27 closures and Nov 28–29 weekend. Four valid days after start are Nov 25, Nov 30, Dec 1, Dec 2.